Review date: 21-02-2021
House repairs
Other (Building)
Lyttelton, Banks Peninsula
4.0
I asked Paul to go ahead with the internal plastering provided it could be done soon, and was told it would take "a couple of weeks". After 2 weeks very little had been done. After I spoke to Paul about the lack of progress, work stopped altogether for the next 2 weeks, and was sporadic after that, taking a total of over 8 weeks to complete. Also, although I made a written request for a quote for the plastering, Paul didn't provide one, resulting in a misunderstanding over the cost.