Project description

Complete defit of the retail space, all ceilings, shopfront, partitions and floor coverings. Patch and plaster walls at completion, and grind floor ready for new shop fitout.
This one was a little tricky, as its not a big shop so we had to be very methodical about how and when we dismantled the various components, or we'd fast run out of room...!
The other challenge was getting the rubbish out, 250m away to the loading dock, over gloss black tile floors. We ended up rolling out floor protection at 4am every morning through the mall to eliminate wheel marks and dust.