Project

Re-leveling in Huntley

Setting up
Setting up
New pile plus packers
New pile plus packers
Packers inserted
Packers inserted
New Pile & short bearer
New Pile & short bearer
Packers inserted
Packers inserted
leveling & Packing
leveling & Packing
Jacked and packed
Jacked and packed
New Pile & short bearer
New Pile & short bearer
New pile
New pile

Project description

Due to subsidence the left side rear portion of the house had sunken. The remedy was to jack and pack existing piles so that area of the house would then be restored back to level and then installed four new piles in between existing to stop further sinking.

Last updated on 30-09-2023