Project

26 Andrew Baxter Dr, Mangere Airport

I/S boundary burst water firemain in driveway
I/S boundary burst water firemain in driveway
O/S boundary overview of burst firemain
O/S boundary overview of burst firemain
driveway excavation exposure
driveway excavation exposure
PE pipe welding renewal works
PE pipe welding renewal works
Above ground mark out of full blown cavity underground
Above ground mark out of full blown cavity underground
Firemain renewal connection #1 n
Firemain renewal connection #1 n
Firemain renewal connection #2
Firemain renewal connection #2
Water Supply - After repairs
Water Supply - After repairs
Water Supply - Before works
Water Supply - Before works
PE Electro-Fusion welding
PE Electro-Fusion welding
Watermain pressure testing
Watermain pressure testing

Project description

150mm S2 burst firemain afterhours - Critical
1m section repair after excavation has been awarded to conduct a full 15m renewal to upgrade to a 180mm PE100 SRD11 PN16 in the driveway plus 30m of 32mm water supply upgrade into a 50mm15m conduit in driveway. Project completed as firemain has been PE welded, pressure tested, installed and livened.

Last updated on 19-03-2024