Project

Watermain Upgrade Installation

PE butt welding - Devear Enterprises
PE butt welding - Devear Enterprises
Directional drilling & excvataion works @ entry point
Directional drilling & excvataion works @ entry point
Lot connection & hydrant installation
Lot connection & hydrant installation
125mm PE100 pipe install with 45deg EF bend and lot connection install
125mm PE100 pipe install with 45deg EF bend and lot connection install
125mm pipe thrusted and exit point
125mm pipe thrusted and exit point
x2 125x32mm lot connection EF tapping bands with x1 125x25mm TB install
x2 125x32mm lot connection EF tapping bands with x1 125x25mm TB install

Project description

24 Tupaki Place, Pakuranga Heights

Last updated on 16-03-2025