Published: 22 September 2017
Small bathroom (approx 2.4m square) wanting tiles on floor and walls. Will need waterproofing done also. Tiles are already at work site. Builder and plumber are scheduled. Tiler can start anytime after 13 October - keen on finishing this soon. Thanks
Workmanship |
1.0
|
Cost |
1.0
|
Schedule |
1.0
|
Communications |
1.0
|
Unfortunately despite starting well, this job never got complete. After 8 weeks since the job started and a variety of reasons/excuses for why the person failed to turn up (or on several occasions made no contact with us at all) we cancelled the agreement. This has cost us a lot more to get another tiler in, plus extra expenses for errors that were made along the way (such as tiling over the hole for the electrical plug) etc. I would not recommend using this person.
Work carried out by the owner/operator
Reviewed on 22-12-2017
Tradesperson reply
"arrived on site after been delayed by the builder, the workmanship was poor, we had to refix gib, many nails bent over, door frame loose and no architrave, channel drain no even set, plus the layout had been totally change, having that we had to go back and finish off the waterproofing and the drain still wasn't fitted correctly, then again we had to re waterproof the insert as the build had fixed the screws through to the bedroom nextdoor, the insert was not even mentioned if the quote,"
Partner with Builderscrack