Larklane and Armstromg Fram Drive

Started from Foundation

Started from Foundation

Cladding done

Cladding done

soffit liner done

soffit liner done

Building papers , windows , installed, tapes and flashings done , Cavity closer cavity battens etc

Building papers , windows , installed, tapes and flashings done , Cavity closer cavity battens etc

Trusses Installed

Trusses Installed

Retaining wall done

Retaining wall done

Retaining walls

Retaining walls

Mid floor done ready for second frames

Mid floor done ready for second frames

Joists nogging done

Joists nogging done

joists done

joists done

Joist's

Joist's

Block wall outsoursed

Block wall outsoursed

frames up . level fixings all done

frames up . level fixings all done

frames

frames

the day when frames were arrived

the day when frames were arrived

Project description

Two projects started and finished at same Time From Foundation to CCC

Last updated on 08-02-2024