Project

Wall Removal

Before load bearing wall discovery

Before load bearing wall discovery

Work stopped due to wall

Work stopped due to wall

After

After

After

After

Existing Floor Plan

Existing Floor Plan

Proposed Floor Plan

Proposed Floor Plan

Project description

After asking a builder to remove two walls so that they could open their living area, it was soon discovered that one was load bearing. I was asked to provide a solution to hold the roof up. After measuring the affected area and discussing options, the client was very happy to have a simple solution while saving money on materials and keeping the structural beam out of view due to limited space within the roof structure. This was done as an exemption so there was also a saving in cost with consenting.

Last updated on 28-02-2023