Firth Hollands Terracotta

Project description

-Excavate existing area to a minimum of 180mm below finish levels.
-Add base course, bedding, screed levels
-Lay new pavers
-Cut pavers to fit where necessary
-Add concrete haunching to retain paving where necessary.
-Fill with paver joints with paver interlocking sand.
-Compact all areas to complete