1. Remove existing built-in shower, bath, vanity and strip back to bare walls. 2. Replace damaged flooring and any affected mouldy framing. 3. Re-jib 4 walls with gib aquiline, gib over ceiling, gib stopping as needed and new architraves etc. 4. Fit new shower, bath and vanity. Install Seratone wet-wall lining around bath and vanity area to window height. 5. Plumbing, electrical and new vinyl flooring to be handled separately.