Final site check Collect supplied turf from local depot. Remove and dump up to 90mm of clean fill. Apply up to 100mm of aggregate, level based on existing contour and compact, final screed to a fine finish ready for turf installation. Supply and install timber edging using 100x50 RS H4 timber with 45x45 H4 timber pegs Lay Geotek matting below gap7 base Lay turf, cut to shape, fix to aggregate base using ground pins at approximately 250mm spacings around the perimeter or fix to a timber plinth if a timber plinth exists using staples and adhesive. Seam seal joins using joining tape if required and then brush in the required amount of infill if required and broom clean area.