- 48m^2 footprint, nominal of 500mm deep - May need to take out a big tree stump, has been dug round. - Foundation to be built and pour as per design - Involve 3 inspections from the geotechnical engineer - All pipe embedded items as per the construction drawing -Sign off works for building consent - Driveway access (2.5meters wide)
Workmanship |
2.0
|
Cost |
4.0
|
Schedule |
4.0
|
Communications |
4.0
|
The start of the work was fine, but the workmanship of concrete finish was disappointing, numerous chipped concrete corners(minor and major), honeycombing, the foundation was not squared and waved a little bit. I have asked the contractor to fix it, they came to fix some but not all of them, I asked them to repair the honeycomb under shower box, and Boss called me on Sunday afternoon and argued saying that was unnecessary, even said what I said was nonsense. I have paid in full, disappoint.
Work carried out by an employee of the company
Reviewed on 13-10-2019