Published: 21 July 2022
Remove existing pinex floor (vinyl already lifted), replace with new sheets
Workmanship |
1.0
|
Cost |
3.0
|
Schedule |
1.0
|
Communications |
1.0
|
Job: floor to be replaced/repaired ready for tiling as pinex swollen/weak, needed more nogs underneath Lloyd & Nick responded, quoted, started work within 24 hrs - grateful. After job ‘completed’ I noticed there was still bounce/movement in kitchen floor, I crawled under house to investigate, found 15 x nogs abandoned & stretches between joists to 1300mm with no nogs. Phoned Lloyd who denied this was so. Texted photos, he said he’d come back to sort that day. Didn’t show/ignoring calls
Work carried out by the owner/operator
Reviewed on 27-07-2022
#1 | Tradie 1 |
|
3 jobs | Secured job |
#2 | Tradie 2 | Not reviewed | 0 jobs | No longer in contact |
#3 | Tradie 3 |
|
27 jobs | No longer in contact |
#4 | Tradie 4 |
|
5 jobs | No longer in contact |