Hi, I live in 603 Coe Road, Hillend Balclutha. I had Bryan Wilson Geo Sun Ltd install an off grid system, its a parallel system with 27 panels and 3 inverters plus a vectron inverter to manage the load from the back up generator. His firm has been liquidated and he has not completed the job. Are you able to finish the system for me? Bloxham Farm The work to be done to complete this project is: Connect Tigo Gateway and power up. Configure Tigo optimisers, ensuring first that all are connected. Secure all cables on the array. Connect Tigo CCA to the internet via Wi-Fi Supply and fit 1 x PylonTech US3000 LiFePOS4 battery. Test charging performance of generator via Victron MultiPlus inverter/charger. We are having trouble with the array charging the batteries quickly, there is 17.5 kw of batteries. Thanks