Outdoor slab required, 7.2m x 3.6m and small extra area for heat pump. 150mm depth, mesh reinforced. Total = 4.2m3 May require one grate/drain and piping approx 3–4m to existing soak pit adjacent to area. Minimal boxing required (one long edge only) as the slab edges will butt up against a retaining wall on three sides. Preparation work on the earth needed with addition of base course and compacting. Area is already dug out, so no other earthworks required. Access is reasonably good. It should be possible to back a truck or mixer within 10m across flat land, though TBC. Work needs to be completed by mid August.