Box, install reinforcing, and pour a 17m x 5m shed foundation with 450mm ground beams -- approximately 27 m3 of concrete total. Ready for DPM and reinforcement next week once the excavation sign-off is complete (planned for Monday the 27th). Note that due to the steep drive, concrete trucks are limited to 3 to 5 cubes per load. Concrete required to be 25 MPa due to corrosion zone D.